Project Schedule

Meetings were held with local community groups, the National Capital Commission and a Municipal Technical Advisory Committee, to review and discuss about the bridge rehabilitations detail designs.

Milestones Date
Contract No. 1
Project Initiation Late Winter 2005
NCC Meeting No. 1 Early Spring 2006
MTAC Meeting No. 1 Early Spring of 2006
Hampton-Iona-Island Park Community Groups Meeting No. 1 Early Spring of 2006
NCC Meeting No. 2 Summer 2006
MTAC Meeting No. 2 Summer 2006
MTAC Meeting No. 3 Fall 2006
Hampton-Iona-Island Park Community Groups Meeting No. 2 Summer 2006
Public Involvement Centre September 12, 2006
MTAC Meeting No. 4 Fall 2006
Hampton-Iona-Island Park Community Groups Meeting No. 3 Fall 2006
Completion of Detail Design Late Fall 2006
Submission of the Design and Construction Report Late Fall 2006
Construction Completed Fall 2007
Contract No. 2
Project Initiation Late Winter 2005
MTAC Meeting No. 1 Late Spring 2007
MTAC Meeting No. 2 Mid Summer 2007
Public Involvement Centre July 12, 2007
Completion of Detail Design Late Summer 2007
Submission of the Design and Construction Report Summer 2007
Construction Completed Fall 2008
Contract No. 3
Project Initiation Late Winter 2005
MTAC Meeting No. 1 TBD
MTAC Meeting No. 2 TBD
Public Involvement Centre April 2, 2009
Completion of Detail Design Summer 2009
Submission of the Design and Construction Report Summer 2009
Construction Completed Summer 2011
Contract No. 4
Project Initiation Summer 2011
Completion of Detail Design Fall 2011
Submission of the Design and Construction Report Fall 2011
Construction to be Completed Summer 2013